Creek Bend Heights Senior Housing Apartment Project

Hamburg, NY

Complete interior and exterior upgrade of a 6-story 130-unit apartment building including apartments, lobby, community rooms, corridor, and elevator lobby improvements. The project also included a complete fire alarm system upgrade and new fire pump and pump controller upgrades.

Challenges

Scheduling was very critical and required the displacement of all the tenants throughout this fully occupied building. Multiple phases and the staged, temporary relocation of the tenants mandated scheduling to the day and perfect synchronization with other trades, as well as inspectors.

Highlights

Project highlights include:

  • A well coordinated teamwork approach coupled with the willingness of all trades to work together pulled off this project remarkably well.
  • High efficiency lighting throughout the interior and exterior of the facility.
  • In ground “well lights” for “invisible” illumination the new signage.
  • A new addressable fire alarm system throughout the facility.
  • New fire pump motors and controllers.

Additional Information